Under IRC section 460, a contract that is not finished in the year it starts must be reported using percentage of completion. Two exceptions let contractors use completed contract instead: residential construction contracts, and contracts of a small contractor that will finish within two years. Which one you fall into depends on your gross receipts and the type of job.

What is a long-term contract for tax purposes?

A long-term contract is a contract for building, installation, construction or manufacturing that is not completed in the tax year it was entered into. Jobs that begin and end in the same year are outside the rule, so most service calls and short remodels never reach it.

The definition is in IRC section 460(f). The date you sign matters, not the date you start work. A contract signed in November that finishes in February is long-term even if the crew only worked six weeks.

Electricians, plumbers, HVAC, roofers and general contractors all run into this when a job crosses December 31. If most of your work is quick turnaround, you may never have a long-term contract.

Which contractors can use the completed contract method?

Two groups: contractors on residential construction contracts, and small contractors whose contract is expected to finish within two years of its start date, provided average gross receipts for the prior three years do not exceed the section 448(c) threshold.

The statute is IRC section 460(e)(1). The threshold was $25 million when the Tax Cuts and Jobs Act set it, and it adjusts for inflation each year. It is $31 million for 2025 (Rev. Proc. 2024-40) and $32 million for tax years beginning in 2026 (Rev. Proc. 2025-32, section 3.30).

Two details trip people up. First, the test looks at three prior years of average gross receipts, not this year's. Second, under section 448(c) related businesses are combined, so an owner with a contracting company and a separate equipment or real estate company needs to run the test on the group.

If you meet the exception, you can report income when the contract is complete. That defers tax on profit from a job that spans years. It also makes a year look better or worse than it really is, which matters when a lender reads your return.

What is a residential construction contract?

It is a contract where at least 80 percent of the estimated total contract costs are for building, constructing, reconstructing or rehabilitating dwelling units, plus improvements to real property directly related to those units and located on the site.

The 2025 tax law (Public Law 119-21, section 70430) widened this exception. Before, it only covered home construction contracts, meaning dwelling units in buildings with four or fewer units. For contracts entered into in tax years beginning after July 4, 2025, it covers residential construction contracts with no unit limit, so apartment and condo projects can qualify. Both definitions are now in IRC section 460(e)(4).

The 80 percent test is applied contract by contract. A contractor with mostly residential jobs can still have a commercial job that does not qualify.

A residential construction contract is exempt from percentage of completion without a gross receipts limit or a time limit. That is the main reason residential builders often stay on completed contract at any size. Larger builders may still have to capitalize costs under section 263A. That applies when a home construction contract is expected to run past two years or the builder fails the gross receipts test. The period is three years for other residential contracts.

How does percentage of completion work?

You report a share of the contract price each year equal to the share of total estimated cost you have incurred so far. This is the cost-to-cost method in IRC section 460(b)(1).

Here is a hypothetical example with round numbers. It is arithmetic for illustration, not a real job.

LineAmountHow it is figured
Contract price$400,000Signed contract
Estimated total cost$300,000Budget
Cost incurred to date$150,000Job cost report
Percent complete50 percent$150,000 / $300,000
Revenue to report$200,00050 percent x $400,000
Billed to date$230,000Invoices
Overbilling (a liability)$30,000$230,000 - $200,000

The overbilling line is why a work-in-progress, or WIP, schedule exists. It shows which jobs are billed ahead of earnings and which are behind. Underbilled jobs mean you have done work you have not collected for yet.

There is an optional 10 percent rule in section 460(b)(5). You can wait to start reporting a contract until at least 10 percent of estimated costs have been incurred.

When a percentage of completion contract is finished, the look-back method in section 460(b)(2) applies. You refigure each prior year using actual costs and price, and interest is charged or paid on the difference, on Form 8697. It does not apply to a contract finished within two years if its gross price is no more than the lesser of $1 million or 1 percent of your average annual gross receipts (section 460(b)(3)(B)).

Can the tax method differ from the financials your surety sees?

Yes. Tax returns can use completed contract while the financial statements given to a lender or surety use percentage of completion. The difference is a book to tax adjustment, and your CPA has to carry it.

For GAAP statements, revenue follows ASC 606. Most construction contracts recognize revenue over time as the work is done, often measured by cost to cost, which works like percentage of completion. Completed contract is a tax method, not a GAAP method, for most of these jobs.

Surety underwriters usually want to see over and under billings and estimated gross profit by job. A tax return that defers profit can make a profitable year look thin on paper. A WIP schedule fixes that without changing your tax method.

That is why our WIP plan, from $2,497 a month, includes a monthly percent-of-completion WIP schedule and over and under billing entries. Prices are on the contractor accounting page.

Can I change methods?

A change in accounting method generally needs IRS consent, requested on Form 3115 under IRC section 446(e). Do not switch just by filing differently one year.

Contractors often cross the gross receipts limit by growing, or lose the exception when a contract is expected to run beyond two years. When that happens, section 460(e)(2)(B) applies the change on a cut-off basis, so only contracts entered into from that year forward switch. Plan for it before the year the limit is crossed, not after.

Also check your cash versus accrual method. Section 448(c) is the same test that governs whether many small businesses can use the cash method, so one gross receipts check tells you about both.

Next step

Bring your last two returns and a list of open jobs to a discovery call. We will tell you which method you are on, whether you are near the limit and what a monthly WIP schedule would look like. We work with contractors and trades nationwide. For related reading see our year end payroll and 1099 checklist, or book a free discovery call.

Frequently asked questions

What is the small contractor exception?

A contractor can use completed contract instead of percentage of completion if the contract is expected to finish within 2 years of starting and average annual gross receipts for the prior three years do not exceed the section 448(c) threshold. See IRC section 460(e)(1)(B).

Does a remodeler count as a residential construction contract?

Often yes. If at least 80 percent of the estimated contract costs are for work on dwelling units, plus related site improvements, it is a residential construction contract under IRC section 460(e)(4). For contracts entered into in tax years beginning after July 4, 2025, that covers apartments and condos as well as homes.

Do I have to use percentage of completion for a job that finishes in the same year?

No. The rule only applies to long-term contracts, which are contracts not completed in the tax year they were entered into.

Does my second company count toward the gross receipts limit?

Often yes. Under section 448(c), businesses treated as one employer under the related party rules are combined for the test.

Why does my surety want a WIP schedule if I use completed contract?

Sureties assess earned revenue, billings and estimated profit by job. A WIP schedule gives them that without changing your tax method.